For Primes & Gov't
For DBEs, VetBiz, etc.
100% US-based
OH-95 Owls Head WRRF Main Substation Replacement
20059591
Arcadis
Brooklyn, Kings County, NY
01/26/2026 at 02:00
The Project includes the following Work:
Construction of New Main Substation No. 1 building single-story concrete and brick type building with temperature control adjacent to existing Substation No. 1 on the main plant entrance road with 27kV to 5kV main transformers (external), switchgear, cabling, and batteries.
1. Installation of four (4) 38 kV metal clad switchgears.
2. Installation of five (5) 5 kV metal clad switchgears.
3. Installation of four (4) 26.4 kV to 4.16 kV Step Down Transformers.
4. Reconnection to the four (4) Con Edison 27 kV service lines.
5. Installation indoor and outdoor including lighting
6. Installation of a fire alarm system, with remote third party monitoring.
7. Installation of substation Monitoring and Control Panels in both Main Substation No. 1 and Pump & Power House (P'PH).
8. Transfer of power from the existing Substation No. 1 to the new Main Substation No. 1 building.
9. Demolition of existing Substation No. 1.
10. Installation of a ductless split system & exhaust fans HVAC system.
11. Installation of landscaping and perimeter decorative fencing.
12. Installation of solar panels on the Main Substation No. 1 building roof for Local Law compliance.
13. Submission to Institute for Sustainable Infrastructure (ISI) for Envision certification for Local Law compliance.
14. Preparation and restoration of an area designated to provide temporary grit container storage area during construction.
15. Preparation of a permanent grit container storage area, re-work associated drainage, and pave areas disturbed by project.
Drawings & Specifications
Contract documents, including plans & specifications can be viewed and downloaded at: https://app.buildingconnected.com/projects/691b595dfb27c2f3191255e6/files
The Bidder will be required to quote in compliance with all project plans and specifications. Non-Disclosure Agreements are provided when applicable. Addenda is posted and notification is sent to all invited bidders.
Insurance Requirements
Upon award, Subcontractors must provide insurance in accordance with our subcontract agreement. A copy of the subcontractor agreement can be found in Building Connected Project Plan Room.
Bonding Requirements
For subcontracts the Bidder shall furnish Performance and Payment Bonds equal to the full subcontract price. For Material Contracts, the bidder shall furnish Supply Bonds in amount equal to full Material Contract price. Bond premiums are reimbursable by Kiewit/Mass. Electric Construction Co. Jett Industries Inc.
Please provide current bond rate with Quote/Proposal or advise if you are unable to bond so that we my address this issue.
Submission of Proposals & Quotes
Proposals & Quotes from Contractors & Suppliers must be submitted on or prior to bid due date listed above. You can submit your quote two (2) ways:
1) Upload your proposal to Building Connected https://app.buildingconnected.com/projects/691b595dfb27c2f3191255e6/files
2) E-mail your quote/ proposal to Project Estimator Listed or procurementwcl@kiewit.com
How to get in touch
Outreach Coordinator
Patricia Salmon
323-574-2432
Project Estimator:
Hanna Majestic
607-206-7649
Tricia Salmon
(201) 571-2697
(201) 571-2600
Address
470 Chestnut Ridge Road
Woodcliff Lake, NJ 7677
The U.S. Department of Transportation-supported Northeast Region SBTRC helps DBEs with Procurement, Capital Access, and Surety Bond Assistance - and much more - at no cost.