Project Name
Silver Lake Storage Replacement Project - Headworks Flow Control Station - PH3 - PACKAGE #7 Flow Control Station HVAC Scope Package
Bid/Contract #
Contract No. 47071-2
Awarding Agency
Los Angeles Department of Water and Power (LADWP)
Project Location
Los Angeles, Los Angeles County, CA
Bid Date
02/18/2022 at 02:00
Project Details
SCOPE OF THIS BID PACKAGE IS COMPRISED OF:
Procurement and installation of all HVAC Systems for Flow Meter Vault, Valve Vaults, and Flow Control Station Vault.
1. Trade Contractor must be responsible for maintenance of laydown area, exclusively for HVAC system work.
2. All excavation, concrete encasement and backfill of underground HVAC ducting/piping to be completed by HVAC trade contractor. Additional excavated soil left over from trenching shall be re-located to an on-site stock pile, at the trade contractor's expense.
3. Scope of work includes all but not limited to; All exhaust fans, supply fans, cooling units, HVAC controls, ducting, ducting supports, fan and blower curbs, standpipe vents, wall penetrations and concrete and reinforcing steel for encasement.
4. Trade Contractor shall furnish and install all low voltage and control conduit, wire and terminations for HVAC system work.
5. Trade contractor shall coordinate HVAC electrical, schedule, and code requirements with other trade contractors.
6. Trade contractor shall include all startup, testing, balancing and commissioning services and startup plans in accordance with the contract drawings and specifications.
7. Scope of work shall include engineering required for all anchoring of equipment and ducting in accordance with the contract drawings and specifications.
8. Installation of the concrete pads that HVAC equipment will be placed on will be completed by others; however, HVAC Trade Contractor shall provide pad dimensions including edge distances required for anchoring.
9. Trade contractor shall provide wall spools and sleeves for installation by concrete contractors.
10. HVAC Trade Contractor to provide layout and templates for Concrete contractors. Trade Contractor to be available for inspection of walls prior to the placement of concrete.
11. Work may require multiple mobilizations; any additional mobilizations needed shall be included in the bid total.
12. Trade Contractor shall provide an allowance of $50,000 for miscellaneous work as directed by WOL. This work to be billed as force account per the contract documents.
Procurement Category
MBE Participation Goals / WBE Participation Goals
Construction 11% 4%
Supplies 2% 1%
Services 4% 2%
Equipment 2% 2%
PLA Requirements enforced.
Link to bidding documents:
https://webcor.box.com/s/fvfdi5c9hd2rb3qlll7hri980xinezjg
How to get in touch
Outreach Coordinator
Jeremy Yablan
Project Estimator
Jeremy Yablan
Telephone
(805) 583-1010
Fax
(805) 582-1126
Address
794 E. Los Angeles Ave.
Simi Valley, CA 93065